Software Development

Efficiency is for Losers

Focusing on efficiency and ignoring effectiveness is the root cause of most software project failures. Effectiveness is producing the intended or expected result. Efficiency is the ability to accomplish a job with a minimum expenditure of time and effort. Effective software projects deliver code that the end users need; efficient projects deliver that code with a minimum number of resources and time.

Sometimes, we become so obsessed with things we can measure, i.e. project end date, kLOC, that we somehow forget what we were building in the first place. When you’re up to your hips in alligators, it’s hard to remember you were there to drain the swamp.
 

Efficiency only matters if you are being effective.

After 50 years, the top three end-user complaints about software are:

  1. It took too long
  2. It cost too much
  3. It doesn’t do what we need

Salaries are the biggest cost of most software projects, hence if it takes too long then it will cost too much, so we can reduce the complaints to:

  1. It took too long
  2. It doesn’t do what we need

The first issue is a complaint about our efficiency and the second is a complaint about our effectiveness. Let’s make sure that we have common definitions of these two issues before continuing to look at the interplay between efficiency and effectiveness.

Are We There Yet?

Are you late if you miss the project end date?

That depends on your point of view; consider a well specified project (i.e. good requirements) with a good work breakdown structure that is estimated by competent architects to take a competent team of 10 developers at least 15 months to build. Let’s consider 5 scenarios where this is true except as stated below:

Under which circumstances is the project late?

 A. Senior management gives the team 6 months to build the software.
 B. Senior management assigns a team of 5 competent developers instead of 10.
 C. Senior management assigns a team of 10 untrained developers
 D. You have the correct team, but, each developer needs to spend 20-35% of their time maintaining code on another legacy system
 E. The project is staffed as expected

Here are the above scenarios in a table:

#
Team
Resource
Commitment
Months Given
Result
A
10 competent developers
100%
6
Unrealistic estimate
B
5 competent developers
100%
15
Under staffed
C
10 untrained developers
100%
15
Untrained staff
D
10 competent developers
65-80%
15
Team under committed
E
10 competent developers
100%
15
Late

 


Only the last project (E) is late because the estimation of the end date was consistent with the project resources available. Other well known variations which are not late when the end date is missed:

  • Project end date is a SWAG or management declared
  • Project has poor requirements
  • You tell the end-user 10 months when the estimate is 15 months.

If any of the conditions of project E are missing then you have a problem in estimation.  You may still be late, but not based on the project end date computed with bad assumptions.

Of course, being late may be acceptable if you deliver a subset of the expected system.

It Doesn’t Work

“It doesn’t do what we need” is a failure to deliver what the end user needs.
How so we figure out what the end user needs?

The requirements for a system come from a variety of sources:

  1. End-users
  2. Sales and marketing (includes competitors)
  3. Product management
  4. Engineering

These initial requirements will rarely be consistent with each other. In fact, each of these constituents will have a different impression of the requirements. You would expect the raw requirements to be
contradictory in places. The beliefs are like the 4 circles to the left, and the intersection of their beliefs would be the black area.
 
 


The different sources of requirements do not agree because:

  • Everyone has a different point of view
  • Everyone has a different set of beliefs about what is being built
  • Everyone has a different capability of articulating their needs
  • Product managers have varying abilities to synthesize consistent requirements

It is the job of product management to synthesize the different viewpoints into a single set of consistent requirements. If engineering starts before requirements are consistent then you will end up with many fire-fighting meetings and lose time.


Many projects start before the requirements are consistent enough. We hope the initial requirements are a subset of what is required. In practice, we have missed requirements and included requirements that are not needed (see bottom of post, data from Capers Jones) The yellow circle represents what we have captured, the black circle represents the real requirements.
 
 

We rarely have consistent requirements when we start a project, that is why there are different forms of the following cartoon lying around on the Internet.

If you don’t do all the following:

  • Interview all stakeholders for requirements
  • Get end-users to articulate their real needs by product management
  • Synthesize consistent requirements

Then you will fail to build the correct software.  So if you skip any of this work then you are guaranteed to get the response, ” It doesn’t do what we need “.

Effectiveness vs. Efficiency

So, let’s repeat our user complaints:

  1. It took too long
  2. It doesn’t do what we need

It’s possible to deliver the correct software late. It’s impossible to deliver on-time if the software doesn’t work. Focusing on effectiveness is more important than efficiency if a software project is to be delivered successfully.

Ineffectiveness Comes from Poor Requirements


Most organizations don’t test the validity or completeness of their requirements before starting a software project. The requirements get translated into a project plan and then the project manager will attempt to execute the project plan. The project plan becomes the bible and everyone marches to it. As long as tasks are completed on time everyone assumes that you are effective, i.e. doing the right thing. That is until virtually all the tasks are jammed at 95% complete and the project is nowhere near completion.


At some point someone will notice something and say, “I don’t think this feature should work this way”. This will provoke discussions between developers, QA, and product management on correct program behavior. This will spark a series of fire-fighting meetings to resolve the inconsistency, issue a defect, and fix the problem. All of the extra meetings will start causing tasks on the project plan to slip.
 


We discussed the root causes of fire-fighting in a previous blog entry. When fire-fighting starts productivity will grind to a halt. Developers will lose productivity because they will end up being pulled into the endless meetings. At this point the schedule starts slipping and we become focused on the project plan and deadline. Scope gets reduced to help make the project deadline; unfortunately, we tend to throw effectiveness out the window at this point.
 
 
 

With any luck the project and product manager can find a way to reduce scope enough to declare victory after missing the original deadline.

The interesting thing here is that the project failed before it started. The real cause of the failure would be the inconsistent requirements. But, in the chaos of fire-fighting and endless meetings, no one will remember that the requirements were the root cause of the problem. What is the cost of poor requirements? Fortunately, WWMCCS has an answer.  As a military organization they must tracks everything in a detailed fashion and perform root cause analysis for each defect (diagram). This drawing shows what we know to be true.
– The longer a requirement problem takes to discover, the harder and more expensive it is to fix!
– A requirement that would take 1 hour to fix will take 900 hours to fix if it slips to system testing.
 
 
 
 

Conclusion

It is much more important to focus on effectiveness during a project than efficiency. When it becomes clear that you will not make the project end date, you need to stay focused on building the correct software.

Are you tired of the cycle of:

  • Collecting inconsistent requirements?
  • Building a project plan based on the inconsistent requirements?
  • Estimating projects and having senior management disbelieve it?
  • Focusing on the project end date and not on end user needs?
  • Fire-fighting over inconsistent requirements?
  • Losing developer productivity from endless meetings?
  • Not only miss the end date but also not deliver what the end-users need?

The fact that organizations go through this cycle over and over while expecting successful projects is insanity – real world Dilbert cartoons.


How many times are you going to rinse and repeat this process until you try something different? If you want to break this cycle, then you need to start collecting consistent requirements. Think about the impact to your career of the following scenarios:

  1. You miss the deadline but build a subset of what the end-user needs
  2. You miss the deadline and don’t have what the end-user needs

You can at least declare some kind of victory in scenario 1 and your resume will not take a big hit. It’s pretty hard to make up for scenario 2 no matter how you slice it. Alternatively, you can save yourself wasted time by making sure the requirements are consistent before you start development. Inconsistent requirements will lead to fire-fighting later in the project.

As a developer, when you are handed the requirements the team should make a point of looking for inconsistent requirements. The entire team should go through the requirements and look for inconsistencies and force product management to fix them before you start developing. It may sound like a waste of time but it will push the problem of poor requirements back into product management and save you from being in endless meetings. Cultivating patience on holding out for good requirements will lower your blood pressure and help you to sleep at night.  Of course, once you get good requirements then you should hold out for proper project estimates.
 
 
 

Make no mistake, I am the biggest “Loser” of them all. I believe that I have made every mistake in the book at least once :-)
 
 

Reference: Efficiency is for Losers from our JCG partner Dalip Mahal at the Accelerated Development blog.

Dalip Mahal

Dalip is a principal consultant at Accelerated Development and has worked his way through all aspects of software development. He started as a software engineer and worked his way through engineering and product management.
Subscribe
Notify of
guest

This site uses Akismet to reduce spam. Learn how your comment data is processed.

2 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments
Hikari .
Hikari .
11 years ago

This article is kinda aimed to noobs, and it ends not teaching anything worthy.

What the heck, a whole team of noobs that can’t handle requirement at all? Doesn’t know about iterations (and you implicitly suggest Waterfall here!!), architecture, and end up fosing and fighting instead of getting things done?! Of course it will end in disaster.

Dalip S. Mahal
11 years ago
Reply to  Hikari .

Hikari, only about 20% of developers are relatively educated. You are correct that the article is aimed at people with less experience, but there are many of those folks out there :-) The point is that many organizations get caught up in efficiency and lose sight of effectiveness. This article is just a wake up call for people who might have gotten caught up in efficiency at the expense of effectiveness. As an interesting side note, we discuss the so called Waterfall methodology with disdain, but the reality is that the Waterfall methodology is just outlining the dependency of relationship… Read more »

Back to top button